Taylor Avenue to close for installation of link
Starting at 8 p.m. Friday, June 3, reopening at 5 a.m., Monday, June 6
Construction of the link connecting employee parking with the medical campus will require Taylor Avenue to close at 8 p.m., Friday, June 3 and reopen by 5 a.m., Monday, June 6. A crane will set the section of the link spanning Taylor Avenue.
The road along the MetroLink tracks will not be accessible from Taylor Avenue. Access will be maintained to all buildings, parking lots and streets off Taylor Avenue. Detours will be marked. Metro buses will be rerouted to enter the Metro bus terminal from the north only.
Contractors will close Taylor Avenue in the same location an additional two weekends this summer from 8 p.m. Friday through 5 a.m. Monday to pour concrete and install glass on the link. Tentatively scheduled weekends are June 24-27 and August 26-29. Reminders about closures and changes to the dates will be communicated.